2022
I Will Build My Church Progress
July 7 Report
Cross has been repainted
Repair/replacement work on the gym roof continues
June 15 Report
Repair/replacement work on the gym roof has begun
April 15 Report
Activities included painting due to the inclement weather. All of the areas receiving the Deep Sea Dive have been painted out. The gym walls will receive their first coat tomorrow 4/16/21. The southern wing of the gymnasium building is approximately 75% complete with painting. Next week's activities will include continuing with interior painting and we will begin exterior painting, specifically on the cross.
March 29 Report
Tasks in progress this week (March 28) include:
Cross has been repainted
Repair/replacement work on the gym roof continues
June 15 Report
Repair/replacement work on the gym roof has begun
April 15 Report
Activities included painting due to the inclement weather. All of the areas receiving the Deep Sea Dive have been painted out. The gym walls will receive their first coat tomorrow 4/16/21. The southern wing of the gymnasium building is approximately 75% complete with painting. Next week's activities will include continuing with interior painting and we will begin exterior painting, specifically on the cross.
March 29 Report
Tasks in progress this week (March 28) include:
- Priming of gymnasium block walls
- Removal of existing ceiling grid in gym
- Preparation for painting in hallways & other rooms
- Submittals for the windows & awning were approved
- Paint color selection
- Removal of exterior rotten wood
- Confirmed with the equipment supplier the size of the boom lift needed to access the cross at the front of the church for pressure washing and painting
- Provided close color matches for the cross and sent those to the Church for approval
- Completed pressure washing of the brick wall adjacent to the church kitchen
- Continue painting in the gymnasium
- Pressure washing of exterior brick work in areas near the gymnasium building
- Contractors meeting on site with roofer to discuss work such as the gutter work that can take place while awaiting the materials for the roof
- Contractors meeting on site to determine the best equipment to access all areas of the cross for repainting
- Electrical contractor to demo existing gym lighting
- Work will soon commence on the removal of existing damaged gutters not connected to the gym building
July 7 Images
June 15 Images
May 20 Images
April 15 Images
March 29 Images
Previous weeks progress